A sample of the work Wicomm has completed for carriers, tower owners and contractors from 2017 to today. Project values range from $50,000 to $5,000,000.

Current Work

ProjectScope
LEO satellite base stations
Multiple states
Ongoing construction of Low Earth Orbit (LEO) satellite base stations across several states.

New Communication Facilities

ProjectScope
New 105′ monopine
Merlin–Galice
Site grading, ~350′ of underground utilities and access road, 8′-diameter × 22′-deep concrete pier, 105′ monopine tower and 200′ of fencing.
New 65′ monopine in a developed lot
Grants Pass
Removed ~1,200 sq ft of asphalt, 5′ × 18′ drilled pier, 55′ retaining wall, equipment foundation, trenched and directionally bored electrical and fiber in the public right-of-way, repaved and restriped.
New 180′ self-support tower
Mt. Bynion
Concrete piers and foundation, tower erection and 400′ of chain-link security fence.
New 60′ monopole
Brush Street
Pad and pier foundation, monopole erection, 400′ of chain-link fence, ~1,000′ of access road and underground electrical and fiber conduit.
New facility on a 70′ shopping-center sign
Woodland
Structural steel, concrete piers and foundations, underground electrical and fiber, CMU masonry wall, welding, saw cutting, curbs, asphalt access road and signage.
New rooftop communication facility
Rooftop – 3-story hotel
Seismic structural steel upgrade, core drilling for beams and conduits, electrical and fiber, concrete piers, curbs and asphalt access road.
Site relocation to a new tower
Etna
Foundation for a new communication building, demolition of the old building and tower, and regrading for drainage.
Temporary wireless facility – Boatnik 2024
Grants Pass
Erected a temporary tower with antennas, radios, coax and electrical to expand coverage for a large public event.

Tower Replacements (Drop & Swap)

ProjectScope
100′ monopole replacement
Grants Pass Fairgrounds
5′ × 22′ drilled pier, new 100′ monopole, security fencing, and demolition of the old tower and pier foundation.
88′ monopole replacement
Sports Park
5′ × 19′ drilled pier, new 88′ monopole, security fencing, and demolition of the old tower and pier foundation.
New tower and old-site demolition
Shasta
New structural steel and equipment on the tower; demolished the old tower, foundation and communication building; backfilled and regraded.

Tower Modifications & Structural Steel

ProjectScope
Mount modification
Ukiah
Removed and replaced structural steel on an existing tower; upgraded radios, antennas, fiber and electrical.
Colocation on an existing tower
Round Valley
Underground electrical and fiber conduit, equipment foundations, tower structural steel, and radio, antenna, fiber and electrical upgrades.
Colocation on an existing tower
Mendocino
Underground electrical and fiber conduit, equipment foundations, tower structural steel, and radio, antenna, fiber and electrical upgrades.
Stealth antenna mount
Newark
Structural steel to support fiberglass panels that conceal antennas on the structure.
Tower access portsCut new access ports in an existing tower and welded reinforcement plates to maintain structural integrity.
6-story building rooftop site
Harriman Ave
Structural steel inside the building to support rooftop equipment; core drilled for conduits from basement to roof.
86′ building rooftop site
Linkville
Structural steel to support rooftop equipment; core drilled through exterior walls and concrete floors, basement to roof.
Single-story building rooftop site
Covelo
Structural steel to support rooftop equipment; core drilled through exterior walls for electrical and communication conduits.

Site Civil, Utilities & Fiber

ProjectScope
Underground utilities and paving
McKinleyville
300′ of underground utilities, 15,000 sq ft of new asphalt, and 5,000 sq ft of slurry seal and restriping.
Underground fiber
Eureka
New underground fiber by directional drilling, with grading, saw cutting and paving.
Underground fiber
Cave Junction
Saw cut an existing road, installed ~730′ of underground fiber conduit, then regraded and repaved.
Access road build and restoration
Lake Shastina
Surveyed, excavated and graded 1,000′ of access road for drilling and soil testing; after the project was cancelled, removed the road and restored the site with native plants.
Landslide access recovery
Cape Sebastian
Installed a temporary bridge after a landslide, then a 60′-tall engineered Eco-Block wall, backfill, grading and access road for permanent access.
Security fencing
Crescent City Airport
Removed and replaced 200′ of chain-link fencing.

Power & Generators

ProjectScope
~50 emergency generator installations
California
Core drilling for electrical conduits, excavation for underground utilities, and rebar and concrete foundations at sites across California.
New generator set
Covelo
Survey, excavation and grading, concrete foundation, underground conduits and alarming.
Power upgrade
Quincy
Core drilled the building for new underground utility power and removed old overhead poles and wire.
Wildfire power restoration
Laughlin
Installed 10 new privately owned power poles and cabling after wildfire damage.

Demolition & Restoration

ProjectScope
Wildfire-damaged site removal
Atlas Peak
Demolished buildings, towers, underground conduits and concrete foundations, then graded and restored vegetation.
Tower and building decommission
Pelican Bay
Demolished a communication building and 180′ tower, including substructures, utilities and access roads, and restored the site to match the surrounding forest.
Tower decommissionDemolished an existing tower and removed its foundation to 11′ below grade.

Inspections & Specialty

ProjectScope
FAA radio repeater station
San Francisco International Airport
Structural steel and equipment installation for a new FAA radio repeater station at SFO.
Post-construction inspection
Redding
Inspected a newly built communication facility against local, federal, engineering and customer specifications.